MAGOFFIN COUNTY CENTRAL
Location
This segment of the Parkway project runs from just west of the Middle Fork of the Licking River to just east of the KY 7/Salyersville interchange. It covers 5.7 miles of roadway, from mile markers 69.6 – 75.3.
Work on the Gifford Road interchange (Exit 70) was completed in November 2016, about a month earlier than expected. Work on both the KY 7/Salyersville interchange (Exit 75) and the KY 30 interchange (Exit 72) were both completed in the summer of 2018. The Magoffin County Central segment was the first segment of the Mountain Parkway Expansion to be completed.
Project Description
- Widen Parkway to four lanes
- Modernize two existing interchanges
- Build a new interchange at Gifford Road
Maps
The maps below illustrate the current design of this segment of the Parkway, following the construction that was completed in 2016.
The maps below are broken down in three smaller segments, based on project portion, for ease of viewing.
Additional Resources
Download high-resolution versions of the project segments maps:
News Updates on this Segment
Mountain Parkway Expansion Progress Report – August 2018
This periodic report includes highlights about work underway on the Mountain Parkway Expansion. Inclement weather…
Mountain Parkway Project Giving Travelers, Workers a Thanksgiving Break
No project delays coming for holiday travelers SALYERSVILLE, Ky. (November 21, 2017) – Thanksgiving travelers…
Mountain Parkway Expansion: October 2017 Progress Report
This periodic report includes highlights about work underway on the Mountain Parkway Expansion. Inclement weather…
Mountain Parkway Traffic Switch Planned Next Week
Ramps to reopen as traffic moves to newly constructed roadway SALYERSVILLE, Ky. (June 14, 2017)…
Mountain Parkway Expansion Progress Report: Week Beginning May 22
This periodic report includes highlights about work underway on the Mountain Parkway Expansion. Inclement weather…
Mountain Parkway Expansion Progress Report: Week Beginning April 17
This periodic report includes highlights about work underway on the Mountain Parkway Expansion. Inclement weather…
Mountain Parkway Expansion Progress Report: Week Beginning March 6, 2017
This periodic report includes highlights about work underway on the Mountain Parkway Expansion. Inclement weather…
Mountain Parkway Expansion Progress Report — Week of December 19, 2016
This periodic report includes information on work underway on the Mountain Parkway Expansion. Inclement weather…