Exit 75 will be improved, redesigned with parkway widening
SALYERSVILLE, Ky. (March 12, 2015) – Crews are starting work in a second section of the Mountain Parkway Expansion. The latest project will widen 1.1 miles of the parkway and make improvements to the KY 7/Salyersville interchange.
The interchange improvements include reconfiguring the westbound exit ramp to KY 7 from the Mountain Parkway and re-aligning the three other ramps at the interchange. (See exhibit below.)
Greer Mining Inc., based in East Bernstadt, Ky., was awarded a $22.2 million contract for the project late last year by the Kentucky Transportation Cabinet. Greer crews have placed road construction signs along the parkway and are beginning to clear trees and vegetation in the project area. Affected utilities also are being relocated.
Limited impacts to traffic are expected at the start of this project.
“This is an important stretch of the Mountain Parkway,” said Marshall Carrier, a KYTC engineer who is project manager for the Mountain Parkway Expansion. “It is one of the busiest parts of the parkway. As we make improvements in this area, travelers will begin to see the dramatic difference this project will make for residents, travelers and businesses in Eastern Kentucky.”
The construction phase of the Mountain Parkway Expansion began in January, when crews with Bizzack Construction LLC began work to widen 1.4 miles of the parkway and create an interchange at Gifford Road. Site work and blasting is continuing in the Gifford Road area.
The two projects are among three slated to begin this year to the west of Salyersville in the Magoffin County Central Section of the Mountain Parkway Expansion. A project to improve the KY 30 interchange (Exit 72) and widen the parkway in that area is scheduled to begin later this year.
Combined, the three projects will widen about 6 miles of the parkway to the west of Salyersville.
Exhibit: KY 7/Salyersville Interchange
About the Mountain Parkway Expansion
The Mountain Parkway Expansion is a 46-mile transportation improvement project that will create a wider, safer connection between Eastern Kentucky and the rest of the Commonwealth. It is a key transportation project designed to close the only gap in a 400-mile, four-lane, high-speed corridor for commerce and mobility across Kentucky from Pikeville to Paducah. The project will widen 30 miles of the existing parkway from two lanes to four lanes, and will extend the parkway another 16 miles by widening KY 114 between Salyersville and Prestonsburg.
In addition to the construction near Salyersville, other segments of the project are undergoing design, right of way, environmental and utility work to quickly bring as much of the project as possible to shovel-ready status.
The preliminary cost estimate for the project is $753 million, but teams of experts are working on value-engineering solutions to lower the cost to Kentucky taxpayers.
Email: [email protected]
Get the latest news on the Mountain Parkway Expansion straight to your inbox.