MAGOFFIN COUNTY WEST

Location

This segment of the Parkway runs from just west of the Cutino-Hager Road overpass to just west of the Middle Fork of the Licking River Bridge. It covers 4.6 miles, from mile markers 65 to 69.6.

Construction began on this segment of the Parkway in the fall of 2019 and is expected to be completed by the end of the 2022 calendar year. The Magoffin County West segment will be the fourth section of the Parkway to be completed.

Project Description

  • Widen Parkway to four lanes
  • Move existing Parkway alignment south to reduce costs and environmental impacts
  • Add interchange at KY 3046 (Kernie-Ova-Seitz Road) to provide local access

Maps

The maps below illustrate planned improvements for this segment of the Parkway, displaying what the Parkway will look like once construction is complete.

The maps below are broken down into four smaller segments for ease of viewing. These maps read from the west end of the project to the east, in descending order.

Section 1
Section 2
Section 3
Section 4